Identify the correct sequence of the Planning Process:

A. Developing premises

B. Selecting an alternative

C. Implementing the plan

D. Setting objectives

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 2

The planning process starts with setting objectives, then developing premises, identifying and evaluating alternative courses of action, selecting an alternative, implementing the plan and finally follow-up action. Among the given steps the correct order is D, A, B, C.