Identify the correct sequence of the Planning Process:
A. Developing premises
B. Selecting an alternative
C. Implementing the plan
D. Setting objectives
Choose the correct answer from the options given below:
Identify the correct sequence of the Planning Process:
A. Developing premises
B. Selecting an alternative
C. Implementing the plan
D. Setting objectives
Choose the correct answer from the options given below:
Solution
✅ Correct Option: 2
The planning process starts with setting objectives, then developing premises, identifying and evaluating alternative courses of action, selecting an alternative, implementing the plan and finally follow-up action. Among the given steps the correct order is D, A, B, C.