What is the correct sequence of Planning process?

A. Selecting an alternative

B. Identifying & Evaluating alternative courses of action

C. Setting objectives & Developing premises

D. Implementing the plan and Follow up action

Choose the correct answer from the options given below:

Solution

Correct Option: 1

The planning process begins with setting objectives and developing premises (C), then identifying and evaluating alternative courses of action (B), selecting the best alternative (A), and finally implementing the plan with follow-up action (D). Hence C, B, A, D.