Arrange the steps in the planning process in a logical sequence

(A) Follow-up action

(B) Setting objectives

(C) Selecting an alternative

(D) Developing premises

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 4

Planning starts with setting objectives (B), followed by developing premises or assumptions about the future (D). After identifying and evaluating alternatives, the best alternative is selected (C). The plan is then implemented and follow-up action (A) is taken to see that plans are executed as scheduled. Sequence: B, D, C, A.