Single use plans are:

A. Budgets

B. Programmes

C. Procedures

D. Projects

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 1

Single-use plans are developed for a one-time event or project and include budgets, programmes and projects. Procedures are standing plans, as they are used repeatedly for recurring activities. Hence only A, B and D are single-use plans.