Identify the correct sequence of Controlling Process:

A. Measurement of actual performance

B. Analyzing deviations

C. Taking corrective action

D. Setting performance standards

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 4

The controlling process begins with setting performance standards, followed by measurement of actual performance, comparison of actual performance with standards, analysing deviations, and finally taking corrective action. Among the listed steps, the order is D, A, B, C.