Choose the correct order of planning process. (A) Developing Premises (B) Evaluating alternative courses (C) Identifying alternative courses of action (D) Implementing the plan Choose the correct answer from the options given below:
Solution
✅ Correct Option: 2
Option 1 -> This sequence suggests evaluating alternatives (B) before identifying them (C), which is illogical as you cannot evaluate options that haven't been identified yet. Option 2 -> This follows the logical planning sequence: first establish premises/assumptions (A), then identify possible courses of action (C), evaluate those alternatives (B), and finally implement the chosen plan (D). Option 3 -> This sequence places evaluation (B) before developing premises (A) and implementation (D) before identifying alternatives (C), which completely disrupts the rational planning flow. Option 4 -> This order suggests identifying and evaluating alternatives before establishing any premises, and developing premises after implementation, which is backwards and impractical. Hence, Option 2: (A), (C), (B), (D) -> The planning process must follow a logical sequence: Developing Premises provides the foundation and assumptions; Identifying alternative courses gives you options to consider; Evaluating alternative courses helps select the best option; and Implementing the plan executes the chosen course of action -> correct