Match List-I with List-II
List-I List-II (A) Standards (I) Setting of Reduction of defects from 10 pc to 5 pc per lot (B) Management by exception (II) Assigning additional workers and equipment to the project. (C) Critical Control Point (III) An attempt to control everything results in controlling nothing. (D) Corrective Action (IV) Focusing on KRAs
Choose the correct answer from the options given below:
Match List-I with List-II
| List-I | List-II |
|---|---|
| (A) Standards | (I) Setting of Reduction of defects from 10 pc to 5 pc per lot |
| (B) Management by exception | (II) Assigning additional workers and equipment to the project. |
| (C) Critical Control Point | (III) An attempt to control everything results in controlling nothing. |
| (D) Corrective Action | (IV) Focusing on KRAs |
Choose the correct answer from the options given below:
Solution
Option 1: (A)-(II), (B)-(I), (C)-(III), (D)-(IV) -> Incorrectly matches Standards with resource allocation and Management by exception with defect reduction targets, which doesn't align with their core meanings.
Option 2: (A)-(I), (B)-(III), (C)-(IV), (D)-(II) -> Correctly matches Standards with setting specific performance targets, Management by exception with the principle of selective control, Critical Control Points with KRAs, and Corrective Action with resource deployment.
Option 3: (A)-(I), (B)-(II), (C)-(IV), (D)-(III) -> Incorrectly pairs Management by exception with corrective actions and Corrective Action with a control principle, reversing their proper relationships.
Option 4: (A)-(III), (B)-(I), (C)-(IV), (D)-(II) -> Incorrectly matches Standards with a management principle and Management by exception with defect reduction, which are conceptually misaligned.
Hence, Option 2: (A)-(I), (B)-(III), (C)-(IV), (D)-(II) -> Standards are measurable benchmarks (defect reduction targets), Management by exception focuses on significant deviations only (selective control principle), Critical Control Points are strategic KRAs requiring monitoring, and Corrective Action involves remedial measures like resource allocation -> correct