Rita has been promoted as the planning head and the company is planning to launch a new product. What will be the correct sequence of the steps in the planning of the new product?
Rita has been promoted as the planning head and the company is planning to launch a new product. What will be the correct sequence of the steps in the planning of the new product?
Solution
Option 1 -> Follows the correct logical planning sequence: objectives first, then premises, evaluation/selection of alternatives, implementation, and finally follow-up action.
Option 2 -> Incorrect sequence as it places "develop the premises" after implementation, whereas premises should be established before identifying alternatives.
Option 3 -> Starts with developing premises before setting objectives, which is wrong. Objectives must be set first. Also missing the crucial evaluation/selection step and follow-up action.
Option 4 -> Completely incorrect sequence - begins with idea generation instead of setting objectives, and implements alternatives before developing premises, which is illogical.
Hence, Option 1 -> This follows the standard planning process: (1) Set objectives - define what to achieve, (2) Develop premises - establish assumptions about future conditions, (3) Evaluate and select alternatives - analyze options and choose the best, (4) Implement the plan - execute the chosen course of action, (5) Follow-up action - monitor and control execution. This logical sequence ensures systematic and effective planning for the new product launch. -> correct