Choose the correct order of controlling process.
(A) Comparison of actual performance with standards
(B) Setting performance standards & measurement of actual performancee
(C) Taking corrective action
(D) Analysing deviations
Choose the correct answer from the options given below:
Choose the correct order of controlling process.
(A) Comparison of actual performance with standards
(B) Setting performance standards & measurement of actual performancee
(C) Taking corrective action
(D) Analysing deviations
Choose the correct answer from the options given below:
Solution
Option 1 -> (A), (B), (C), (D) - This sequence starts with comparison before setting standards, which is illogical as you cannot compare performance without first establishing standards.
Option 2 -> (A), (C), (B), (D) - This sequence attempts comparison and corrective action before setting standards and measurement, which is incorrect.
Option 3 -> (B), (A), (D), (C) - This follows the logical controlling process: first set standards and measure performance, then compare with standards, analyze deviations, and finally take corrective action.
Option 4 -> (C), (B), (D), (A) - This sequence starts with corrective action before any standards are set or performance measured, which is illogical.
Hence, Option 3: (B), (A), (D), (C) -> The controlling process follows a systematic sequence: (B) Setting performance standards & measurement of actual performance → (A) Comparison of actual performance with standards → (D) Analysing deviations → (C) Taking corrective action. This is the standard management control cycle where standards are established first, then performance is measured and compared, deviations are analyzed, and finally corrective actions are implemented -> correct