Arrange the following steps in planning process in the correct order:

A. Developing premises

B. Setting objectives

C. Selecting an alternative

D. Evaluating alternative courses

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 3

The planning process begins with setting objectives (B), followed by developing premises or assumptions about the future (A). After identifying alternative courses of action, the alternatives are evaluated (D) and finally the best alternative is selected (C). Hence B, A, D, C.