Since the future cannot be predicted with absolute accuracy, ___________ premises may not be fully reliable.

Solution

✅ Correct Option: 2

Option 1 -> Delegating involves assigning tasks and authority to subordinates, which is more about present organizational structure rather than future predictions.

Option 2 -> Planning involves setting objectives and determining future courses of action based on assumptions and forecasts about future conditions, making its premises inherently uncertain.

Option 3 -> Coordination focuses on harmonizing current activities and efforts across different departments or individuals in the present.

Option 4 -> Controlling involves monitoring current performance against standards and taking corrective actions, primarily dealing with present comparisons.


Hence, Option 2: Planning -> Planning is inherently future-oriented and relies on premises, assumptions, and forecasts about future conditions, resources, markets, and events. Since the future is uncertain and cannot be predicted with complete accuracy, the premises on which plans are based may not be fully reliable, making planning subject to limitations and requiring flexibility -> correct