Arrange the following steps of a company's planning process in the correct sequence.

(A) Develop premises

(B) Set objectives

(C) Select an alternative

(D) Implement the plan

Choose the correct answer from the options given below:

Solution

✅ Correct Option: 4

Option 1 -> Starting with developing premises before setting objectives is illogical as you need to know your goals first.

Option 2 -> Selecting alternatives before setting objectives doesn't make sense as alternatives are chosen to achieve objectives.

Option 3 -> Implementing the plan before selecting an alternative is incorrect as you need to choose a course of action first.

Option 4 -> Follows the logical planning sequence: first set objectives (what to achieve), then develop premises (assumptions/forecasts), then select best alternative (decision-making), and finally implement the plan (execution).


Hence, Option 4: (B), (A), (C), (D) -> This represents the correct planning process sequence where objectives are set first to provide direction, premises are developed to create a planning foundation, an alternative is selected from available options, and finally the plan is implemented -> correct