The correct sequence of process of controlling in Samaya doll manufacturing ltd. is:
A. Counting the no. of dolls manufactured
B. Setting a target of manufacturing 50 dolls per day
C. The acceptable range of deviations is 45
D. Comparing of actual performance with standards
Choose the correct answer from the options given below:
The correct sequence of process of controlling in Samaya doll manufacturing ltd. is:
A. Counting the no. of dolls manufactured
B. Setting a target of manufacturing 50 dolls per day
C. The acceptable range of deviations is 45
D. Comparing of actual performance with standards
Choose the correct answer from the options given below:
Solution
The controlling process runs as: setting performance standards, measuring actual performance, comparing actual performance with standards, and then analysing deviations against the acceptable range. Here, setting the 50-doll target (B) is the standard, counting dolls made (A) is measurement, comparison (D) follows, and checking deviations against the acceptable limit of 45 (C) comes last. Hence B, A, D, C.