Match the LIST-I with LIST-II
LIST-I
Work Studies LIST-II
Explanation A. Method Study I. To determine the number of workers to be employed; frame suitable incentive schemes and determine labour costs. B. Motion Study II. Assembly line production C. Time Study III. To determine the amount and frequency of rest intervals in completing a task. D. Fatigue Study IV. The study of movements like lifting, putting objects, sitting and changing positions, etc.
Choose the correct answer from the options given below:
Match the LIST-I with LIST-II
| LIST-I Work Studies | LIST-II Explanation |
|---|---|
| A. Method Study | I. To determine the number of workers to be employed; frame suitable incentive schemes and determine labour costs. |
| B. Motion Study | II. Assembly line production |
| C. Time Study | III. To determine the amount and frequency of rest intervals in completing a task. |
| D. Fatigue Study | IV. The study of movements like lifting, putting objects, sitting and changing positions, etc. |
Choose the correct answer from the options given below:
Solution
✅ Correct Option: 3
Method study finds the one best way of doing a job; Taylor's assembly line production is its application (II). Motion study analyses movements like lifting, putting objects and changing positions (IV). Time study determines standard time, helping decide worker numbers, incentive schemes and labour costs (I). Fatigue study determines the amount and frequency of rest intervals (III). Hence A-II, B-IV, C-I, D-III.
Related questions:
2025: 24 May Shift 1
2022: 30 Aug Shift 1