If there is a plan to increase production then more labour and more machinery will be required. This step would also involve organizing for labour and purchase of machinery. Identify this step in the process of planning.

Solution

Correct Option: 2

Once a plan is chosen, it has to be put into action. Arranging additional labour and purchasing machinery to execute the production plan belongs to the Implementing the Plan step of the planning process.