CUET Business StudiesBusiness Studies > MediumDeviationCritical point controlBreak-even analysisCritical path method✅ Correct Option: 2Related questions:22 May Shift 1Arrange the following steps of controlling process in a correct sequence: (A) Comparison of actual performance with standards (B) Setting standards (C) Analysis of deviations and taking corrective action (D) Measuring actual performance Choose the correct answer from the options given below:30 May Shift 1Which of the following statements are not correct? (A) Planning and controlling are essentially one and the same. (B) Controlling is the part of planning process. (C) Controlling can be a substitute for planning. (D) Planning without controlling is meaningless. Choose the correct answer from the options given below:24 May Shift 1The criteria against which actual performance is measured in the process of controlling are called: