(A) Analysing deviations

(B) Measurement of actual performance

(C) Setting up standards

(D) Comparison of actual performance with standards

Identify the correct sequence of Controlling process:

Solution

Correct Option: 4

The correct sequence is:

  1. Setting standards ->
  2. Measuring actual performance ->
  3. Comparing with standards ->
  4. Analysing deviations

Correct sequence is: (C) -> (B) -> (D) -> (A)

So, answer is: 4