Mr. Sumit Sharma is the Product manager of a Garment manufacturing company. He was asked by the Senior manager Mr. Ram to prepare performance report of the employee as the production was decreasing.

Which step of the controlling process, the senior manager Mr. Ram wanted Mr. Sumit to perform?

Solution

Correct Option: 3

Mr. Ram asked Mr. Sumit to prepare a performance report of employees, which involves measuring what the employees have actually achieved. This corresponds to the measurement of actual performance step, which comes before comparison with standards, analysis of deviations, or corrective action.