Skip to main contentSkip to solution

Arrange the following steps followed during the planning process in a proper sequence.

A. Developing premises

B. Evaluating alternative courses

C. Selecting an alternative

D. Setting an Objective

E. Identifying alternative courses of action

Solution

Correct Option: 3

The standard planning process sequence is: setting objectives, developing premises, identifying alternative courses of action, evaluating alternative courses, selecting an alternative, implementing the plan, and follow-up. Matching the given items: D (Setting an alternative/objective) comes first, then A (Developing premises), then E (Identifying alternatives), then B (Evaluating alternatives), then C (Selecting an alternative). The correct order is D, A, E, B, C.

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question