Arrange the following steps followed during the planning process in a proper sequence.
A. Developing premises
B. Evaluating alternative courses
C. Selecting an alternative
D. Setting an Objective
E. Identifying alternative courses of action
Arrange the following steps followed during the planning process in a proper sequence.
A. Developing premises
B. Evaluating alternative courses
C. Selecting an alternative
D. Setting an Objective
E. Identifying alternative courses of action
Solution
The standard planning process sequence is: setting objectives, developing premises, identifying alternative courses of action, evaluating alternative courses, selecting an alternative, implementing the plan, and follow-up. Matching the given items: D (Setting an alternative/objective) comes first, then A (Developing premises), then E (Identifying alternatives), then B (Evaluating alternatives), then C (Selecting an alternative). The correct order is D, A, E, B, C.
Related questions:
2025: 21 May Shift 1
2025: 15 May Shift 1
2026: 31 May Shift 1