Q1:
2026: 6 June Shift 1
Arithmetic
Time & Work
Easy
Jayati and Archana can do a piece of work in 10 days and Jayati can do the same work in 12 days. In how many days can Archana do the same work alone?
2026: 6 June Shift 1
Arithmetic
Time & Work
Easy
Jayati and Archana can do a piece of work in 10 days and Jayati can do the same work in 12 days. In how many days can Archana do the same work alone?
2026: 31 May Shift 2
Arithmetic
Time & Work
Easy
A is twice as good as a workman B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
2026: 31 May Shift 1
Arithmetic
Time & Work
Easy
Abhimanyu can do 25% of a piece of work in 5 days. How many days will he take to complete the work ten times ?
2026: 30 May Shift 2
Arithmetic
Time & Work
Easy
35 women can do a work in 15 days. How many women would be required to do the same work in 25 days?
2026: 30 May Shift 1
Arithmetic
Time & Work
Medium
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work?
2026: 29 May Shift 2
Arithmetic
Time & Work
Easy
A and B together can complete a piece of work in 12 days. A alone can complete the work in 15 days. In how many days can B alone complete the same work?
2026: 29 May Shift 1
Arithmetic
Time & Work
Easy
A, B and C can complete a work in 7 days. If A and B complete the work together, they take 10 days. How much time will C take in completing the work alone ?
2026: 26 May Shift 1
Arithmetic
Time & Work
Easy
A is twice as good a worker as B, and together they finish a piece of work in 16 days. In how many days will A alone finish the work?
2026: 25 May Shift 2
Arithmetic
Time & Work
Easy
A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same work ?
2026: 25 May Shift 1
Arithmetic
Time & Work
Medium
P can complete a work in 20 days while Q is 25% more effiecent than P. Q worked for 6 days and left, remaining work is completed by R in 15 days. Find in how many days R can complete the whole work alone?
2026: 24 May Shift 1
Arithmetic
Time & Work
Easy
Neha can complete a work in 6 days and Ishrat can complete the same work in 4 days. What will be the time taken by them to complete the same work together ?
2026: 22 May Shift 2
Arithmetic
Time & Work
Easy
Mohan can dig a well in 15 days, Shyam is 25% better than Mohan. How many days does Shyam alone can take to dig the same well?
2026: 21 May Shift 2
Arithmetic
Time & Work
Medium
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days, altogether, was the work completed?
2026: 21 May Shift 1
Arithmetic
Time & Work
Easy
A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same work?
2026: 20 May Shift 2
Arithmetic
Time & Work
Medium
A can do a work in 36 days, while B can do the same work in 48 days. If A works for x days while B works for x + 2 days, then one-third of the work is completed. Find the value of x?
2026: 20 May Shift 1
Arithmetic
Time & Work
Medium
Raj, Mayank and Neer, can complete a work in 30, 35 and 28 days, respectively.
Consider the following statements.
(A) Raj and Mayank, together will complete the work in days.
(B) Mayank, and Neer, together will complete the work in days.
(C) Raj and Neer, together will complete the work in days.
(D) Raj, Neer, and Mayank, together will complete the work in days.
Choose the correct answer from the options given below:
2026: 19 May Shift 2
Arithmetic
Time & Work
Medium
40 men can complete a work in 48 days. 56 men started for the same work for x days. After x days, 16 men increased, so, the remaining work is completed in days. Find x?
2026: 18 May Shift 2
Arithmetic
Time & Work
Easy
X is twice as good a workman as Y and together they finish a piece of work in 18 days. In how many days will X alone finish the work?
2026: 18 May Shift 1
Arithmetic
Time & Work
Medium
Work done by A in one day is half of the work done by B in one day. Work done by B is half of the work done by C in one day. If C alone can complete the work in 35 days, then in how many days can A, B and C together complete the work?
2026: 14 May Shift 2
Arithmetic
Time & Work
Easy
A completes a work in 7 days. B completes the same work in 9 days. What will be the time taken in completing the same work if both A & B work together?
2026: 14 May Shift 1
Arithmetic
Time & Work
Easy
Vandana can do a piece of work in 25 days. Vasvi is 25% more efficient then Vandana. The number of days taken by Vasvi to do the same piece of work is:
2026: 12 May Shift 2
Arithmetic
Time & Work
Easy
X, Y and Z complete a work in 6 days. X or Y alone can do the same work in 16 days. In how many days can Z alone finish the same work?
2026: 12 May Shift 1
Arithmetic
Time & Work
Medium
The construction work is assign to the Group-I of 7 workers. They complete the task in 12 days. The another Group-II started the same task with same number of workers. They started the work and just after 5th day their 2 workers left the work. Now, in how many days this Group will complete the task ?
2025: 3 June Shift 2
Arithmetic
Time & Work
Easy
P and Q can do work separately in 10 and 20 days, respectively. In how many days can they finish it, working together?
2025: 3 June Shift 1
Arithmetic
Time & Work
Medium
Ajeeta and Sanjeeta undertake a project for ₹ 48000. Further, it is known that Ajeeta can finish the project in 24 days and Sanjeeta can finish the project in 40 days while working alone. If the project gets completed in just 10 days when Ranjeeta also helped them in completing the project, then determine the amount that Ranjeeta would have received, if they distributed the amount in proportion to their respective working capability?
2025: 3 June Shift 1
Arithmetic
Time & Work
Medium
X, Y and Z together can do a piece of work in 16 (4/11) days. X and Y together can do the same work in 20 days. In how many days will Z alone finish the 60% of the work?
2025: 2 June Shift 2
Arithmetic
Time & Work
Medium
30 boys are engaged to do a piece of work in 15 days but it is found that in 5 days, 3/5 work is completed. How many boys may be allowed to go off, so that the work may be finished on time?
2025: 30 May Shift 2
Arithmetic
Time & Work
Medium
To complete a work, Aditi takes 60 % more time than Bimla. If both of them work together, they take 16 days to complete the work. How much time shall Bimla take to do it alone?
2025: 29 May Shift 2
Arithmetic
Time & Work
Medium
Arrange the following cases in ascending order in terms of number of days to complete the same work.
(A) P can do (1/3)rd of the work in 5 days.
(B) Q can do (1/6)th of the work in 4 days.
(C) R can do 25% of the work in 4 days.
(D) S can do 35% of the work in 7 days.
Choose the correct answer from the options given below:
2025: 29 May Shift 1
Arithmetic
Time & Work
Medium
P completed part of certain work in 12 days. Further, Q completed the rest of the work in 18 days. In how many days could P and Q complete the work, if they worked together?