A and B together can complete a piece of work in 12 days. A alone can complete the work in 15 days. In how many days can B alone complete the same work?
A and B together can complete a piece of work in 12 days. A alone can complete the work in 15 days. In how many days can B alone complete the same work?
Solution
✅ Correct Option: 3
One day's work of B .
So B alone takes 60 days.