AfterBoards Logo
Free Daily RCsForumsExplore PlatformAttempt PYPs
Home
Home
›Past Year Questions
›JIPMAT
›Arithmetic
›Time & Work

JIPMAT Arithmetic > Time & Work PYQs

Filter & Analyse PYQs (Topic-Wise) →

No login required. No pop-ups. We have all previous-year questions with solutions for free!

CUET General TestCUET MathematicsIIM Bangalore (BBA-DBE)IIM Bangalore (UGAT)IPMAT IndoreIPMAT RohtakJIPMAT

Q1:

JIPMAT 2025

Arithmetic > Time & Work

Medium

40 men can complete a work in 48 days. 64 men started and did the same work for $x$ days. After $x$ days, 32 men increased, so, the remaining work is completed in $16\frac{2}{3}$ days, then the value of $x$ is

Answer options
Correct Answer
Option 1
Correct Answer
Explanation →

Q2:

JIPMAT 2024

Arithmetic > Time & Work

Hard

A is $40 \%$ less efficient than $B$ who can do the same work in $20 \%$ less time than $C$. If $A$ and B together can complete $80 \%$ work in 12 days, then in how many days $60 \%$ work can be completed by $\mathrm{B}$ and $\mathrm{C}$ together ?

Answer options
Correct Answer
Option 3
Correct Answer
Explanation →

Q3:

JIPMAT 2023

Arithmetic > Time & Work

Hard

<p>Given below are two statements:</p> <p>Statement (I): 4 boys and 8 girls completed 1/3 of work in 5 days. After that 3 boys and 3 girls increased, and they completed another 1/3 of work in 3 days. If the remaining work is to be completed in 2 days, then the number of girls that should be increased is 32.</p><p> Statement (II): The ratio of time taken by A and C to do a work is 1:2 respectively. B is 166 (2/3)% more efficient than C. Time taken by A to complete 6% of work is 6 days.</p><p>Then, the time taken by B and C together to complete the whole work is 54 (6/11) days.</p> <p>In light of the above statements, choose the most appropriate answer from the options given below.</p>

Answer options
Correct Answer
Option 4
Correct Answer
Explanation →

Q4:

JIPMAT 2022

Arithmetic > Time & Work

Easy

If A can do 1/4 of a work in 3 days and B can do 1/6 of the same work in 4 days, how much will A get if both work together and are paid Rs. 180 in total?

Answer options
Correct Answer
Option 4
Correct Answer
Explanation →

Q5:

JIPMAT 2021

Arithmetic > Time & Work

Medium

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished?

Answer options
Correct Answer
Option 2
Correct Answer
Explanation →

Q6:

JIPMAT 2021

Arithmetic > Time & Work

Medium

4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women finish it?

Answer options
Correct Answer
Option 4
Correct Answer
Explanation →

JIPMAT Past Year Questions (Topic-Wise):

Logical Reasoning

  • Coding & Decoding
  • Logical Sequence
  • Puzzles
  • Directions
  • Reflection
  • Clocks & Calendar
  • Odd One Out
  • Bar Graph
  • Blood Relations
  • Dices & Cubes
  • Syllogism
  • Venn Diagram
  • Tabular Data
  • Ranking
  • Arrangements
  • Pie Chart
  • Analogy

Verbal Ability

  • Parajumbles
  • Figures of Speech
  • Reading Comprehension
  • Vocabulary
  • Parasummary
  • Spelling
  • Idioms & Phrasal Verbs
  • Verbal Analogies
  • Grammar

Arithmetic

  • Ratio, Proportion & Variation
  • Time, Speed & Distance
  • Mixture & Alligation
  • Time & Work
  • Profit & Loss
  • Simple & Compound Interest
  • Averages
  • Percentages

Geometry

  • Circles
  • Triangles
  • Coordinate Geometry
  • Trigonometry
  • Quadrilaterals
  • Polygons
  • Solids

Grammar

  • Tenses
  • Active & Passive Voice
  • Subject Verb Agreement
  • Parts of Speech
  • Direct & Indirect Speech
  • Grammatical Error
  • Punctuations

Number System

  • Remainder
  • Factorisation
  • Integral Solutions
  • HCF & LCM
  • Unit Digit
  • Miscellaneous
  • Divisibility Rules

Algebra

  • Linear Equation
  • Indices
  • Quadratic Equations
  • Progression & Series
  • Identities

Vocabulary

  • Synonym
  • Idioms
  • Definition
  • Phrases
  • Antonym

Critical Reasoning

  • Course of Action
  • Statement & Conclusion
  • Assertion & Reason

Modern Math

  • Probability
  • Permutation & Combination
  • Set Theory
AfterBoards Logo

Made with ♥ by Guru Oranges AfterTech Pvt. Ltd.

© 2026 All rights reserved

Daily RCsVideosTopic TestsMocksAll PYQsContact