A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days, altogether, was the work completed?
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for 2 days and then A was replaced by B. In how many days, altogether, was the work completed?
Solution
✅ Correct Option: 2
One day's work: A , B , C .
A and C in 2 days: . Remaining .
B and C together do per day, needing days.
Total days.
Related questions:
2026: 30 May Shift 2
2026: 14 May Shift 1
2022: 17 Aug Shift 1
2022: 8 Aug Shift 1
2025: 27 May Shift 1