A completes a work in 7 days. B completes the same work in 9 days. What will be the time taken in completing the same work if both A & B work together?

Solution

✅ Correct Option: 1

In one day A does 1/71/7 of the work and B does 1/91/9.

Together they do 17+19=1663\frac{1}{7} + \frac{1}{9} = \frac{16}{63} per day.

Time taken =6316= \frac{63}{16} days.