CUET General Test - Arrange the following cases in ascending order in terms of number of days to complete the same work. (A) P can do (1/3)rd of the work in 5 days. (B) Q can do (1/6)th of the work in 4 days. (C) R can do 25% of the work in 4 days. (D) S can do 35% of the work in 7 days. Choose the correct answer from the options given below: | PYQs + Solutions | AfterBoards