CUET General Test - The construction work is assign to the Group-I of 7 workers. They complete the task in 12 days. The another Group-II started the same task with same number of workers. They started the work and just after 5th day their 2 workers left the work. Now, in how many days this Group will complete the task ? | PYQs + Solutions | AfterBoards