A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same work ?
A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same work ?
Solution
✅ Correct Option: 1
Efficiency and time are inversely proportional.
If A's efficiency is , B's is , so the ratio of efficiencies is and the ratio of times is .
Time for B days.