A and B, working separately can do a piece of work in 12 days and 20 days respectively. If they work alternately, beginning with A, then in how many days can the work be completed?
A and B, working separately can do a piece of work in 12 days and 20 days respectively. If they work alternately, beginning with A, then in how many days can the work be completed?
Solution
A can complete the work in 12 days, so A's work in 1 day
B can complete the work in 20 days, so B's work in 1 day
They work alternately, with A starting first.
In one complete cycle of 2 days:
Day 1: A works and completes of the work
Day 2: B works and completes of the work
Work completed in 2 days
Number of complete 2-day cycles needed:
In 2 days: work completed
In 14 days (7 cycles): work completed
Remaining work
After 14 days, it is A's turn to work on day 15.
A completes work in 1 day.
Since , A can finish the remaining work in less than a day.
Time required by A to complete remaining work
day
Total time to complete the work days
Since the work is completed during the 15th day, the answer is 15 days.
Related questions:
2023: 19 June Shift 1
2026: 26 May Shift 1
2022: 17 Aug Shift 1
2023: 21 May Shift 1
2025: 29 May Shift 1