P completed part of certain work in 12 days. Further, Q completed the rest of the work in 18 days. In how many days could P and Q complete the work, if they worked together?
P completed part of certain work in 12 days. Further, Q completed the rest of the work in 18 days. In how many days could P and Q complete the work, if they worked together?
Solution
P completed of the work in 12 days.
Q completed the remaining part.
Remaining work
Q completed of the work in 18 days.
P's work rate per day:
of the work per day
P alone can complete the entire work in 30 days.
Q's work rate per day:
of the work per day
Q alone can complete the entire work in 30 days.
Combined work rate when P and Q work together:
of the work per day
Days needed to complete the work together:
days
Therefore, P and Q working together can complete the work in 15 days.
Related questions:
2026: 25 May Shift 2
2023: 15 June Shift 2
2022: 26 Aug Shift 1