A and B can do a work in 9 days and 12 days respectively. If they work on alternate days starting with A, then in how many days will the work be completed?
A and B can do a work in 9 days and 12 days respectively. If they work on alternate days starting with A, then in how many days will the work be completed?
Solution
✅ Correct Option: 3
A's 1-day work = , B's 1-day work = .
In 2 days (A then B): .
In 10 days (5 cycles): work done. Remaining: .
On day 11, A works: time = day.
Total = days.