8 men and 3 boys together can complete a piece of work in 5 days. If 5 boys can complete the same piece of work in 15 days, in how many days do 5 men complete the same piece of work?

Solution

✅ Correct Option: 4

The work involves 3 pieces of information:

  • 8 men + 3 boys together finish work in 5 days
  • 5 boys alone finish the same work in 15 days
  • Need to find: 5 men alone will take how many days

5 boys finish the work in 15 days.

Total work =5×15=75= 5 \times 15 = 75 boy-days

One boy's one day work =175= \dfrac{1}{75} of total work


8 men + 3 boys finish work in 5 days.

Work by 8 men in 5 days =8×5=40= 8 \times 5 = 40 man-days

Work by 3 boys in 5 days =3×5=15= 3 \times 5 = 15 boy-days

Total work =40= 40 man-days +15+ 15 boy-days

Since total work =75= 75 boy-days:

4040 man-days +15+ 15 boy-days =75= 75 boy-days

4040 man-days =60= 60 boy-days

11 man-day =1.5= 1.5 boy-days


Total work =75= 75 boy-days

Converting to man-days:

Total work =751.5=50= \dfrac{75}{1.5} = 50 man-days

For 5 men:

Days needed =505=10= \dfrac{50}{5} = 10 days


Therefore, 5 men complete the same piece of work in 10 days.