If 36 persons can finish 50% of work in 12 days In how many days 72 person can finish the complete work?
If 36 persons can finish 50% of work in 12 days In how many days 72 person can finish the complete work?
Solution
✅ Correct Option: 4
36 persons finish 50% of work in 12 days, so 36 persons finish the complete work in 24 days.
By inverse proportion, 72 persons finish the same work in days.