If 36 persons can finish 50% of work in 12 days In how many days 72 person can finish the complete work?

Solution

Correct Option: 4

36 persons finish 50% of work in 12 days, so 36 persons finish the complete work in 24 days.

By inverse proportion, 72 persons finish the same work in 36×2472=12\frac{36 \times 24}{72} = 12 days.