A can do 14\frac{1}{4}th part of work in 12 days, B can do 50% work in 20 days , and C can do 13\frac{1}{3}rd of the same work in 15 days. Who complete the work first?

Solution

Correct Option: 2

A: 14\frac{1}{4} in 12 days means full work in 48 days. B: 50% in 20 days means full in 40 days. C: 13\frac{1}{3} in 15 days means full in 45 days. B finishes earliest.