A can do th part of work in 12 days, B can do 50% work in 20 days , and C can do rd of the same work in 15 days. Who complete the work first?
A can do th part of work in 12 days, B can do 50% work in 20 days , and C can do rd of the same work in 15 days. Who complete the work first?
Solution
✅ Correct Option: 2
A: in 12 days means full work in 48 days. B: 50% in 20 days means full in 40 days. C: in 15 days means full in 45 days. B finishes earliest.