Skip to main contentSkip to solution

A, B and C can do some work in 40 days. A and C together can do twice as much work as B alone. Find the time taken by B to do the whole work.

Solution

✅ Correct Option: 1

When solving work problems, work rate represents how much work someone completes in 1 day. If someone finishes work in 10 days, their work rate is 110\frac{1}{10} per day.

Work rate =1Time taken to complete whole work= \frac{1}{\text{Time taken to complete whole work}}


Let bb = B's work rate (portion of work B does in 1 day)

Let aa = A's work rate (portion of work A does in 1 day)

Let cc = C's work rate (portion of work C does in 1 day)

Given that A, B, and C together finish the work in 40 days, their combined work rate is 140\frac{1}{40} of the work per day.

a+b+c=140a + b + c = \frac{1}{40}


Given that A and C together can do twice as much work as B alone:

a+c=2ba + c = 2b


Substituting a+c=2ba + c = 2b into the first equation:

2b+b=1402b + b = \frac{1}{40}

3b=1403b = \frac{1}{40}

b=1120b = \frac{1}{120}


If B's work rate is 1120\frac{1}{120} per day, then B completes the whole work in 120 days.

Therefore, the answer is 120 days.

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question