Skip to main contentSkip to solution

Mohan asked 36 men to build his house in 30 day. 50% of the work got completed in just 10 days. So, Mohan removed some workers. Now, how many persons does he need to complete the remaining work in decided time?

Solution

Correct Option: 2

36 men did half the work in 10 days, so they would finish the whole in 20 days. For the remaining half work in 20 days, required men =36×1020=18= \frac{36 \times 10}{20} = 18.

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question