Mohan asked 36 men to build his house in 30 day. 50% of the work got completed in just 10 days. So, Mohan removed some workers. Now, how many persons does he need to complete the remaining work in decided time?

Solution

✅ Correct Option: 2

36 men did half the work in 10 days, so they would finish the whole in 20 days. For the remaining half work in 20 days, required men =36×1020=18= \frac{36 \times 10}{20} = 18.