JIPMAT 2021Arithmetic > Easy24323640✅ Correct Option: 4Watch NowPeople (of same rates)Related questions:JIPMAT 2021A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished?JIPMAT 2022If A can do 1/4 of a work in 3 days and B can do 1/6 of the same work in 4 days, how much will A get if both work together and are paid Rs. 180 in total?JIPMAT 202540 men can complete a work in 48 days. 64 men started and did the same work for xxx days. After xxx days, 32 men increased, so, the remaining work is completed in 162316\frac{2}{3}1632 days, then the value of xxx is