Skip to main contentSkip to solution

18 women complete a work in 24 days and 24 men complete the same work in 15 days. 16 women worked for 3 days and then they left. 20 men worked for the next 2 days, and then they are joined by 16 women. In how many days will they finish the remaining work?

Solution

✅ Correct Option: 3

Total work can be expressed in units:

  • 18 women complete work in 24 days → Total work = 18 × 24 = 432 woman-days
  • 24 men complete work in 15 days → Total work = 24 × 15 = 360 man-days

Using LCM of 432 and 360 = 2160 units as total work:

Work rate per person per day:

  • 1 woman's 1 day work = 2160 ÷ 432 = 5 units/day
  • 1 man's 1 day work = 2160 ÷ 360 = 6 units/day

Work done by 16 women for 3 days:

Work done = 16 × 3 × 5

Work done = 240 units


Work done by 20 men for 2 days:

Work done = 20 × 2 × 6

Work done = 240 units


Total work = 2160 units

Work completed = 240 + 240 = 480 units

Remaining work = 2160 - 480

Remaining work = 1680 units


Combined daily work rate when 20 men and 16 women work together:

Daily work rate = (20 × 6) + (16 × 5)

Daily work rate = 120 + 80

Daily work rate = 200 units/day


Days needed = 1680 ÷ 200

Days needed = 8.4 days

Days needed = 8258\frac{2}{5} days

Therefore, they will finish the remaining work in 8258\frac{2}{5} days.

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question