A and B can complete a piece of work in 30 days. B and C in 10 days, which C and A in 5 days. If all of them work together, the time taken in completing the work

Solution

Correct Option: 3

Add the three rates: (A+B)+(B+C)+(C+A) = 1/30 + 1/10 + 1/5 = 10/30. So 2(A+B+C) = 1/3, giving A+B+C = 1/6. Together they finish in 6 days.