Let P, Q, and R represent the number of days each person takes to complete the work alone.
P and Q together finish in 60 days, so they complete 601 of the work per day.
Q and R together finish in 120 days, so they complete 1201 of the work per day.
P and R together finish in 90 days, so they complete 901 of the work per day.
This gives:
P1+Q1=601 ... (1)
Q1+R1=1201 ... (2)
P1+R1=901 ... (3)
Adding all three equations:
(P1+Q1)+(Q1+R1)+(P1+R1)=601+1201+901
2(P1)+2(Q1)+2(R1)=601+1201+901
The LCM of 60, 120, and 90 is 360.
601=3606
1201=3603
901=3604
3606+3603+3604=36013
Therefore:
2(P1+Q1+R1)=36013
P1+Q1+R1=72013
From equation (3): P1+R1=901
Subtracting this from the sum:
(P1+Q1+R1)−(P1+R1)=72013−901
Q1=72013−901
Converting 901 to denominator 720:
901=7208
Q1=72013−7208
Q1=7205
Q1=1441
Therefore, Q alone can complete the work in 144 days.