A completes of a work in 10 days. Then he completes the remaining work with the help of B in 5 days. The time required for A and B together to complete the entire work is:
A completes of a work in 10 days. Then he completes the remaining work with the help of B in 5 days. The time required for A and B together to complete the entire work is:
Solution
✅ Correct Option: 2
Remaining work after A's part = . A and B together complete of the work in 5 days. So their combined one-day work = . Time for full work together = days.