JIPMAT 2021Arithmetic > Easy24323640✅ Correct Option: 4Watch NowPeople (of same rates)Related questions:A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished?Given below are two statements: Statement (I): 4 boys and 8 girls completed 1/3 of work in 5 days. After that 3 boys and 3 girls increased, and they completed another 1/3 of work in 3 days. If the remaining work is to be completed in 2 days, then the number of girls that should be increased is 32. Statement (II): The ratio of time taken by A and C to do a work is 1:2 respectively. B is 166 (2/3)% more efficient than C. Time taken by A to complete 6% of work is 6 days.Then, the time taken by B and C together to complete the whole work is 54 (6/11) days. In light of the above statements, choose the most appropriate answer from the options given below.If A can do 1/4 of a work in 3 days and B can do 1/6 of the same work in 4 days, how much will A get if both work together and are paid Rs. 180 in total?