Alice can complete a certain work in 24 days. Bob is twice as efficient as Alice. Both of them worked together for x days and stopped. The remaining work was completed by Carol working alone for (x+1) days. If Carol is 25 % less efficient than Bob, then the total number of days it took to complete the whole work was
Alice can complete a certain work in 24 days. Bob is twice as efficient as Alice. Both of them worked together for x days and stopped. The remaining work was completed by Carol working alone for (x+1) days. If Carol is 25 % less efficient than Bob, then the total number of days it took to complete the whole work was
Solution
Alice completes the work in 24 days, so her work rate = of the work per day.
Bob is twice as efficient as Alice, so Bob's work rate = of the work per day.
Carol is 25% less efficient than Bob. This means Carol works at 75% of Bob's efficiency.
Carol's work rate = of the work per day.
When Alice and Bob work together for days:
Combined work rate = of the work per day.
Work completed by Alice and Bob =
Carol then works alone for days:
Work completed by Carol =
Since the entire work is completed:
Multiplying throughout by 16:
Total days to complete the work = Days Alice and Bob worked + Days Carol worked
Total days = days
The answer is Option 3: 11.