A can do a work in 4 days, B can do same work in 8 days, then the time taken by A and B to do the same work together is:
A can do a work in 4 days, B can do same work in 8 days, then the time taken by A and B to do the same work together is:
Solution
✅ Correct Option: 1
When A can do work in 4 days, in 1 day A completes of the work.
When B can do work in 8 days, in 1 day B completes of the work.
A's rate work per day
B's rate work per day
When A and B work together, their rates are added:
Combined rate
work per day
Time
days
Therefore, A and B together complete the work in days.