Iimb BbadbeArithmetic > Medium30361827✅ Correct Option: 1Related questions:IIM-B (BBA-DBE) 2025 #1A and C together can complete a certain work in 30 days. B is 20% more efficient than C. A, B and C together can do the same work in 20 days. C alone completed one fourth of the work and the remaining work was completed by A and B together. In how many days was the entire work completed?IIM-B (BBA-DBE) 2024 #1Sahil can complete a job in 20 days when working alone. Manoj is twice as fast as Sahil and three times as fast as Ashish in the same jo The collaborative work arrangement involves Sahil and Manoj working on the first day, Sahil and Ashish on the second day, and Manoj and Ashish on the third day. This three-day cycle continues till the work is complete What fraction of the total work will then be done by Ashish till the job is completed?IIM-B (BBA-DBE) 2024 #2A, B and C work in a workshop for creating identical idols. A can craft 10 idols in 150 days. Similarly, B and C can individually create 16 idols in 192 days and 320 days, respectively. B works every day, A works only on alternate days starting from the first day, i.e. 1st March, and C also works only on alternate days starting from the second day, i.e 2nd March. On which date will the construction of 2 idols be completed?