IPMAT Rohtak 2019Arithmetic > Medium52 days42 days30 days50 days✅ Correct Option: 4Related questions:81 equally efficient people could complete a piece of work in 15 days. Initially 45 such people started working together. But after they worked together for 6 days their employer wanted that the work should be completed in a total of 21 days. However any new worker who joins is only 60% as efficient as any of the 45 people already working. How many new workers did the employer hire to work alongside the initial 45 people to meet the deadline?Amisha can complete a particular task in twenty days. After working for four days she fell sick for four days and resumed the work on the ninth day but with half of her original work rate. She completed the task in another twelve days with the help of a co-worker who joined her from the ninth day. The number of days required for the co-worker to complete the task alone would be4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women finish it?