IPMAT Rohtak 2019Arithmetic > Medium52 days42 days30 days50 days✅ Correct Option: 4Related questions:A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished?Given below are two statements: Statement (I): 4 boys and 8 girls completed 1/3 of work in 5 days. After that 3 boys and 3 girls increased, and they completed another 1/3 of work in 3 days. If the remaining work is to be completed in 2 days, then the number of girls that should be increased is 32. Statement (II): The ratio of time taken by A and C to do a work is 1:2 respectively. B is 166 (2/3)% more efficient than C. Time taken by A to complete 6% of work is 6 days.Then, the time taken by B and C together to complete the whole work is 54 (6/11) days. In light of the above statements, choose the most appropriate answer from the options given below.Sahil can complete a job in 20 days when working alone. Manoj is twice as fast as Sahil and three times as fast as Ashish in the same jo The collaborative work arrangement involves Sahil and Manoj working on the first day, Sahil and Ashish on the second day, and Manoj and Ashish on the third day. This three-day cycle continues till the work is complete What fraction of the total work will then be done by Ashish till the job is completed?