Arrange the following in correct order with respect to steps in project-based learning:

(A) Guidance and Monitoring

(B) Defining a Plan

(C) Identification of Project

(D) Outcome of Project

Solution

✅ Correct Option: 2

A project starts by choosing what to work on, then the plan is made, the work is guided and monitored, and the outcome is reached at the end.

(C) Identification of Project: choose the problem or topic to work on

(B) Defining a Plan: decide the objectives, tasks, resources and timeline

(A) Guidance and Monitoring: the teacher guides students and checks progress while they carry out the plan

(D) Outcome of Project: the final product or result, which is presented and evaluated