A project is divided into various manageable modules, and each of the modules has a well-defined task to be performed with a set of inputs. This approach to a project means:

Solution

✅ Correct Option: 1

A structured approach breaks a project into smaller, manageable modules. Each module has a well-defined task, a known set of inputs and an expected output. This is top-down, modular decomposition, which makes the project easier to design, test, assign and maintain.


Option 3: an unstructured approach is ad hoc, with no clear division into modules or defined tasks.