Arrange the following steps of project based learning:

A. Guidance and Monitoring

B. Defining a plan

C. Identification of project

D. Outcome of project

Solution

✅ Correct Option: 1

A project is first chosen, then planned, then carried out under guidance, and finally its outcome is presented and assessed.

C. Identification of project: the topic or problem is selected.

B. Defining a plan: objectives, tasks, resources and timeline are set.

A. Guidance and Monitoring: the teacher supervises and supports students while they work.

D. Outcome of project: the final product or report is presented and evaluated.


Option 4: guidance and monitoring happen during the work, so they come before the final outcome, not after it.