_________ approach to a project means that a project is divided into various manageable modules, and each of the modules has a well-defined task to be performed with a set of inputs.
_________ approach to a project means that a project is divided into various manageable modules, and each of the modules has a well-defined task to be performed with a set of inputs.
Solution
A modular approach breaks a project into smaller, manageable modules. Each module has a well-defined task and works on a given set of inputs to produce outputs. Modules can be developed, tested and reused independently, and then combined to build the complete system.
Option 1: an unstructured approach has no such division into well-defined parts, so it is the opposite of what the question describes.
Option 3: teamwork concerns how people collaborate, not how the project itself is divided into modules.