Arrange the following steps in correct order for solving projects:

(A) Fixing of a time frame and processing

(B) Defining a plan

(C) Providing guidance and monitoring

(D) Identification of Project

Solution

✅ Correct Option: 4

The project begins with choosing what to do, then planning it, then running it to a schedule, and finally guiding and monitoring the work.

(D) Identification of Project: decide what the project will be.

(B) Defining a plan: lay out what is to be done and how.

(A) Fixing of a time frame and processing: set deadlines and carry out the work.

(C) Providing guidance and monitoring: support the learners and keep checking progress.