Arrange the following steps in correct order for solving projects:
(A) Fixing of a time frame and processing
(B) Defining a plan
(C) Providing guidance and monitoring
(D) Identification of Project
Arrange the following steps in correct order for solving projects:
(A) Fixing of a time frame and processing
(B) Defining a plan
(C) Providing guidance and monitoring
(D) Identification of Project
Solution
✅ Correct Option: 4
The project begins with choosing what to do, then planning it, then running it to a schedule, and finally guiding and monitoring the work.
(D) Identification of Project: decide what the project will be.
(B) Defining a plan: lay out what is to be done and how.
(A) Fixing of a time frame and processing: set deadlines and carry out the work.
(C) Providing guidance and monitoring: support the learners and keep checking progress.